History
The Town Center Community Redevelopment Area, encompassing approximately 517 acres, was established by Resolution on March 3, 1998, with an extension to 2037. The area is located north of US 98, and bounded substantially by Airport Road to the east and north, and Beach Drive on the west.
2025 Projects:
Continued progress with the undergrounding of the existing utilities from Marler Bridge to Airport Road. A large portion of this segment (identified as Phase 1) lies within the Town Center CRA. The drilling of conduit pathways began in the fall of 2024 and proceeded through 2025. The TCCRA has committed $4 million total to this project (approximately $266K/year).
The undergrounding project above aligns with the overall goal of safety within the Town Center CRA Master Plan. The Town Center CRA is optimistic about their healthy fund balance and continues to identify meaningful projects that can be pursued in the upcoming years.
Links:
City Budget (contains CRA budgets)
City Audits (contains CRA audits)